Wind Turbine of the Month - Nordex N175/6.X Delta4000
Technical information, data, and photos of the Nordex N175-6.X Delta4000 wind turbine
Hello everyone and welcome to a new issue of Windletter. I'm Sergio Fernández Munguía (@Sergio_FerMun) and here we discuss the latest news in the wind power sector from a different perspective. If you're not subscribed to the newsletter, you can do so here.
Windletter is sponsored by:
🔹 Tetrace. Reference provider of O&M services, engineering, supervision, and spare parts in the renewable energy market. More information here.
🔹 RenerCycle. Development and commercialization of specialized circular economy solutions and services for renewable energies. More information here.
🔹 Nabrawind. Design, development, manufacturing, and commercialization of advanced wind technologies. More information here.
Windletter está disponible en español aquí
We are launching a new section in Windletter in collaboration with Pablo Carazo, a contributor to Windtechs. For those unfamiliar, Windtechs is a consultancy and Market Intelligence firm specialised in wind turbine technology.
Each month, Pablo and I will bring you an analysis of one of the main wind turbines available on the market, both onshore and offshore.
If you do not want to miss any of them, subscribe here.
Windletter is a publication supported by its community of readers. If you enjoy the content, you can subscribe for free or become a paid subscriber to support the publication.
Nordex N175-6.X Delta4000
The N175/6.X is Nordex’s bet in the large-rotor onshore segment. The wind turbine is part of the Delta4000 family, a platform that Nordex has progressively scaled with models such as the N149/5.X and the N163/6.X.
With a 175-metre rotor and a power rating of up to 7 MW, it is designed specifically for low- and medium-wind sites, where it promises annual energy production increases of 7–14% compared to previous models.
Recently, Nordex was celebrating 40 GW installed of the Delta4000 platform since its launch in September 2017. Although the truth is that Nordex groups under the same platform models ranging from the N133/4.8 to the N175/6.X, with noteworthy technical differences between them.

Main specifications
Rated power: 6.22 MW (up to 7 MW depending on site conditions)
Rotor / Swept area: 175 m / 24,053 m2
Power density: 291 W/m2 (at 7 MW)
Hub heights / Towers:
Steel: from 112 to 142 m
Hybrid (concrete–steel): up to 179 metres, with versions developed in-house and others from third parties. A 200-metre hybrid version was announced, although later 199 has been mentioned.
Drivetrain: High Speed DFIG
IEC 61400-1 class: Class S
Cut-in / Cut-out: 3–20 m/s
Noise: 106 dB at 6.22 MW
Design lifetime: 25 years, extendable to 35.
Climatic variants:
Normal Climate Version: –20 °C to +40 °C (there may be derating)
Cold Climate Version: cold climates from –30 °C to +40 °C (there may be derating)
Certification: TÜV SÜD Type Certificate
Architecture and design
Drivetrain:
Main shaft: supported by a single spherical roller main bearing in the typical 3-point suspension configuration, with the gearbox torque arms acting as the other two support points.
Gearbox: high-speed, three-stage gearbox (two planetary stages and one helical gear stage). It is equipped with journal bearings instead of rolling bearings on the planetary gears.
Electrical system:
6-pole DFIG generator.
Partial converter located in the nacelle.
Transformer located in the nacelle, immersed in ester.
SF6 medium-voltage switchgear, located at ground level.
Pitch: electric, with a three-stage planetary gearbox per blade and a brake integrated into the motor itself.
Yaw: 7–8 geared motors depending on the site’s climatic conditions. It has a double-row ball bearing with four-point contact and brakes integrated into the drive motors themselves.
Blade:
85.7 m in length
Manufactured in glass fibre and carbon in the main spar (sparcap)
Double-row ball bearing with four-point contact
Tested at the Fraunhofer Institute for Wind Energy Systems IWES (Bremerhaven)
Installed prototypes
112 m steel tower, Schleswig-Holstein (Germany), in July 2024
179 m hybrid tower, Santow in Mecklenburg-Western Pomerania (Germany), in January 2025
In-house manufacturing
Blades: Lumbier (Spain) and Rostock (Germany)
Nacelles: Barasoain (Spain) and Rostock (Germany)
Track record and commercial pipeline
The N175/6.X will be available worldwide, but Nordex expects the main demand to be in Europe.
As of September 2025, Nordex reported that the N175/6.X had already reached almost 2,000 MW in sales, including key markets such as Germany, Spain, Canada, Finland, Greece, Italy, Portugal, and Latvia.
Competitors
Siemens Gamesa SG7.0-170
Enercon E175 EP5 E2 (7.0 MW)
Goldwind GWH175-7.8 MW / GWH170-7.2 MW
Envision EN-171/8.X
Sources and links
For a full due diligence of this platform, contact Windtechs.
Thank you very much for reading Windletter and many thanks to Tetrace, RenerCycle and Nabrawind our main sponsors, for making it possible. If you liked it:
Give it a ❤️
Share it on WhatsApp with this link
And if you feel like it, recommend Windletter to help me grow 🚀
See you next time!
Disclaimer: The opinions presented in Windletter are mine and do not necessarily reflect the views of my employer.